Skip to content

Magazine for digital value creation in the construction and real estate industry

Planning down to the last rivet: how BIM and GIS are bringing the Siemensbahn back on track

No trains have run on Berlin's Siemensbahn since 1980. Now the nearly 100-year-old line is to reopen, complete with listed stations, bridges and an 800-metre elevated viaduct. A digital model of the existing infrastructure, containing more than 300,000 components, provides the foundation. Combined with GIS, it supports planning far beyond the individual structure.

28/09/2026 · 5 min

Black-and-white photograph of the Siemensbahn steel viaduct and its concrete supports.
Share this article

Moss between the sleepers, rust on steel girders, trees and shrubs along the route: more than four decades of disuse have left visible marks on the Siemensbahn. Built around 100 years ago by Siemens & Halske, the roughly 4.5-kilometre line served the industrial area through the stations at Gartenfeld, Wernerwerk and Siemensstadt. It has been out of service since 1980 and is now set to rejoin the S-Bahn network. This is not simply a project to build a new railway connection. A substantial part of the historic infrastructure is to be preserved and brought back into use.

It is an ambitious project. Alongside the alteration and new construction of 30 bridge structures, it involves rebuilding the three stations with accessible facilities and connecting the line to Berlin's S-Bahn ring via Jungfernheide. Working with the listed structures, including the roughly 800-metre elevated viaduct, is particularly demanding.

The first work began there in late June 2026. On a test section of the steel viaduct, Deutsche Bahn is initially examining how to repair the historic structure. The findings will inform the wider restoration. Under the current schedule, the Siemensbahn is due to reopen in 2029.

When reconstruction comes before planning

The challenge:  On a new construction project, the digital model develops alongside the design. With an almost 100-year-old steel structure, the sequence is reversed: the existing structure must first be reconstructed digitally before design work can begin.

At Wernerwerk station and the adjoining bridges, surveying, BIM and GIS service provider ARC-GREENLAB undertook this work with its partners. The Siemensbahn engineering consortium, comprising Sweco and KREBS+KIEFER, is responsible for the design. Technology from Esri is used to connect BIM and geospatial data.

ARC-GREENLAB used laser scanning to survey the existing infrastructure, including the viaduct structures and Wernerwerk station's entrance building, roof structure and stairwells. The measurements produce a three-dimensional point cloud representing the structure's existing geometry.

Even a high-resolution laser scan cannot capture every detail unambiguously. ARC-GREENLAB's specialists therefore supplemented the scans with manual measurements on the structure itself. They recorded the number, arrangement and spacing of rivets and checked other fasteners. This process produced an exceptionally detailed BIM model of the existing Siemensbahn infrastructure.

The viaduct was modelled at Level of Detail 400 (LoD 400). The model contains more than 300,000 individual components. The installed steel elements were represented with a maximum tolerance of two millimetres. Even the smallest fasteners are included.

The point cloud thus gradually becomes a structured description of the actual construction. After processing the survey data, the team modelled, checked and corrected the components, then added fasteners and attached information to individual components. Following clash detection, three BIM submodels were created and exported as IFC models of the existing infrastructure.

This level of detail serves a practical purpose. The model provides the geometry and information needed to plan repairs. It can be used for quantity take-offs and to verify structural reassessments against the infrastructure that is actually present.

A structure that, for decades, existed mainly in historic drawings and in its physical form therefore becomes a reliable basis for design once again.

Diagram illustrating the integration of BIM and GIS, featuring Autodesk and ArcGIS products, with roles like designers and GIS managers.ARC Greenlab

BIM knows the bridge - GIS knows its surroundings

However detailed a BIM model may be, it stops at the boundaries of the structure. That perspective is not enough for a railway line. Where does the viaduct sit in the landscape? Which buildings adjoin the route? What planning information is available for the surrounding area? How does an individual structure fit into the line as a whole?

This is where GIS comes in. While BIM describes the structure down to component level, a geographic information system adds spatial context. Siemensbahn's BIM models are therefore combined with relevant geospatial data, including local development and land-use plans, terrain and surface models, and cadastral information. The highly detailed model of an individual viaduct no longer stands alone: it becomes part of a wider spatial picture of the route and its surroundings.

Esri provides the connection between BIM and geospatial data through its ArcGIS GeoBIM technology. The application links detailed infrastructure models with geospatial data, placing them in the context of the entire route. It also connects to Autodesk Construction Cloud, where BIM and project data are managed.

This allows participants to move between the detailed infrastructure model and the wider spatial view without first having to combine data from different systems into a new model. That is particularly useful for linear infrastructure such as the Siemensbahn: BIM depicts individual components in detail, while GIS shows how the structure relates to the route, terrain and surroundings.

Old railway bridge with rusty beams and missing tracks, surrounded by barbed wire and overgrown with grass under a clear blue sky.ARC-GREENLAB GmbH

1 / 5

A rusty, weathered metal bridge with rivets, surrounded by trees and a distant building under a partly cloudy sky.ARC-GREENLAB GmbH

2 / 5

A surveying instrument on a tripod beside the disused Siemensbahn railway bridge.ARC-GREENLAB GmbH

3 / 5

Digital model of the Siemensbahn railway corridor within the surrounding urban landscape.ARC-GREENLAB GmbH

4 / 5

Digital model of the Siemensbahn viaduct with blue markers along the structure.

5 / 5

From individual rivets back to the bigger picture

Designers can explore individual structural connections in the BIM model, then zoom out to see the structure within the entire route. They can also analyse spatial relationships, such as elevation profiles, a structure's immediate surroundings and sightlines.

The real value lies in combining two perspectives, rather than in the 3D display alone. BIM describes the structure in detail, while GIS places it in its spatial context. Together, they provide a more complete picture of the project and make it easier to design and assess complex infrastructure.

The link between BIM and GIS goes further. ArcGIS GeoBIM can associate comments, notes and documents with a specific location in the project. BIM issue management displays tasks and problems directly against the relevant object. Opening an issue reveals its description, cause, deadlines and linked documents, among other details.

Dashboards show the current project status, while a time slider allows users to follow changes over time. Linking BIM and GIS therefore delivers more than a visualisation. The digital model becomes an interface through which project participants can find information, locate problems and associate tasks with locations.

External video from Vimeo - loads only after you click. Privacy policy

Digitalisation starts with existing infrastructure

The Siemensbahn shows what digitalisation in infrastructure construction can mean beyond creating a new 3D model. It begins with the physical infrastructure, which is surveyed, checked and modelled in enough detail for designers to work with it. BIM organises that information at component level. GIS adds spatial context. Linking it with project information and documents then makes the data usable in day-to-day workflows.

This is particularly important for historic infrastructure. Before project participants can decide what to preserve, reinforce, replace or build anew, they must understand what is actually there. At the Siemensbahn, that digital understanding extends to the individual rivet and far beyond the individual structure.

More on this topic

Infrastructure

From megaproject to standard: how Poland is advancing BIM

Between Warsaw and Łódź, Port Polska is developing a new international airport linked to a high-speed rail and road network. The project is among the most ambitious infrastructure programs in Europe and is digitally organized from the start. BIM, shared data environments, and open standards are intended to bring together hundreds of project participants. In 2026, the country is the official partner country of BIM World MUNICH.

29.09.2026

Infrastructure

Hamburg Central Station: coordinating complex construction projects with a digital twin

Hamburg Central Station faces a complex programme of parallel construction projects. A digital twin supports efficient coordination across projects: 4D simulations identify conflicts over space and time while the station remains operational and help resolve them. The semantic data model and its integration with existing IT systems also connect construction planning with day-to-day building operations.

29.09.2026